Ridings - the main layout through to date


return

one of the big tasks was the construction of the Town Centre buildings. These modules are now more-or-less complete, and form self-contained operating railway, bus and trolleybus systems. Further work will finish the remaining details, while working on an Extension!
The most exciting addition to this part is the system of overhead wires for the trolleybuses. In order to have the trolleybus working for the 2005 Sheffield Exhibition, this was limited to one loop of wiring from end to end on the layout and was very successful after some fine tuning. Later work would include frogs (points) and crossings to enable the trolleybuses to travel on different routes; this work can be seen on the Overhead page.
After an exhibition season work continued on the buildings shown below. With the next Sheffield Exhibition looming, work was limited to completing part-finished projects, and making things work better, such as the overhead joiners between the boards. That exhibition went very well, with more learned about setting up and operating. The overhead joiners were not as good as expected, so a more successful improved version was developed. After that, attention turned to buildings again; finishing the block of flats and shops, some trees appeared, as did more overhead wires (see Overhead page), then the station building and footbridge, which was ready for the Huddersfield Railway Modellers Exhibition at the end of October 2006. After the latter exhibition, the decision was made to start on the extension, but also the main boards are still being gradually improved. Finished areas include the Park, with its magnificent stone statue, an office block and shops to fill the last 'hole' on the town board, and the roundabout.
I then decided to go DCC for the trolleybuses. The main motivators for this were that the overhead is very difficult to section, and road vehicles often operate close together, so two in the same section would not be individually controllable, and trying to pass trolleybuses from one section to another would be quite difficult anyway. Therefore, a simple Bachmann E-Z Command Controller was obtained, the trolleybus chipped and tested. It worked well! I don't need fancy controls, or the ability to operate hundreds of vehicles this way. The 10 limit and the minimal functions (like lights) of this unit are fine for this application. However, a Trix hand-held command station has been obtained to do the CV programming.
A
s 2010 opened, I realised that I had actually done little on the layout in 2009. It had been to two exhibitions but had not progressed; this was partly because I had worked on Walford Arches (on older trolleybus layout now owned by the Model Bus Federation). I therefore had to get going again in order to exhibit at the Huddersfield Railway Modeller's October 2010 exhibition in Holmfirth. I started by getting several things finished, as the exhibition had prompted the possibility of Ridings being featured in the Railway Modeller, which it was in 2011 (see main Ridings page for details and link to photos). 2012 was spent working mainly on the extension, but 2013 saw work on the DCC electrics for the road points as can be seen below. Attention has now turned to improving the frogs (overhead points) so that I can extend the overhead circuit. More of this on the Overhead page when I've made some progress!
During 2015, Ridings once again went to the Sheffield Model Railway, Bus and Tramway Exhibition, the last time the event would be held in the centre of Sheffield. This included a new Huddersfield trolleybus on the layout, but apart from that, little layout work had taken place. That is until late in the year, when various decisions were made about the trolleybus circuit and railway expansion. The railway has long needed a fiddle yard and work started on this. Provision had been made to access sliding-type storage tracks off Board 6 but it needed to be upgraded a bit, and plans were laid out for the fiddle yard construction. This continues into 2017, as does the work on the trolleybus overhead.

A new angle was explored early in 2017. The layout has been needing signals and with the introduction of Train-Tech's semi-automatic signals I decided to install seven of these and also three Eckon signals which could be linked to points. Progress is shown below.

Note that this page will continue to chart the progress of the main boards, and the work on the new extension will be detailed on their own devoted pages.
(>>) indicates a larger shot is available. Click on the arrows or the photo.

P1140010a.JPG (93294 bytes)

The Town Hall  (which emulates Bradford City Hall) mocked up to check for fit after shortening some of the sides. The main entrance wall is coloured as delivered in the kit, but the long decorative side on the left was experimentally blackened to see if this matched the pictures of town centre buildings of the time.

P2020033a.JPG (108726 bytes)

Disappointingly, for such an ornate and colourful kit, this is exactly what public buildings looked like in the 1960's before smokeless zone legislation and stone-cleaning, so the whole building would have to be the darkened in the same way. Here is the main entrance side again, treated as such, and the steps reduced to one side only.

P2020032a.JPG (93419 bytes)
The Town Hall would boast a tall clock tower when completed, and I anticipated a quite magnificent building. The detail on this kit is tremendous! This end was changed from brick to stone to be more in keeping with the area.
Also in shot is the skeleton of a flats and shops building in position to check its look. These would eventually have to be built-in to the slope of the layout.
P2120035a.JPG (88321 bytes)
The tower makes an appearance, followed by the roof and other small details (picture on the right >)
P3090102a.JPG (69259 bytes)
P3090105a.JPG (85249 bytes)
The finished article. Very impressive, and complements the town scene very well at this end of the layout.  (>>)
P6270142a.JPG (77790 bytes)

The block of flats and shops started. Here is the shop part underneath just prior to finishing. The kit has been converted from multiple units to a large Woolworth's store and a Boots at the right-hand end. (>>)

P6280146a.JPG (85036 bytes)
The flats section almost built.
P7100010a.JPG (78004 bytes)
The finished block installed on the layout, complete with scenery, people and a car park. These views also shows the overhead at this end.  (>>)
P7100015a.JPG (110347 bytes) P7100013a.JPG (81226 bytes)
Two more views. From the front (on the left) and from the rear (above), the latter showing the block of flats on its pillars. A church is in the background.
PA060024a.JPG (92816 bytes)
The next job was the station. Here the walls are cut out, detailed and 'flat-packed' ready for assembly. The station is scratchbuilt and it and the location are based on Armley Canal Road. The large opening is for the footbridge.
PA060025a.JPG (112241 bytes)
Trial fit in position on the layout.
PA100027a.JPG (76221 bytes)

The complex roof with its skylight in position, and the guttering, chimney stacks and doorway awning being prepared.

PA110028a.JPG (108254 bytes)
The Station building almost finished - just some detailing to do. Next job is the footbridge. (>>)
PA140034a.JPG (93193 bytes)
The main footbridge components made up from a substantially altered kit. As in the prototype location, the walkway will be covered.
PA250076a.JPG (108404 bytes)
Walling and road details now added.  (>>)
PA250065a.JPG (103810 bytes)

View of the completed station area from the platform side.

PA250075a.JPG (81410 bytes)
Low level view of the finished footbridge. The whole station dismantles for transporting the layout.
PA250074a.JPG (82253 bytes)
View along the lifted siding towards the finished station and footbridge.
PB270144a.JPG (98871 bytes)
The park area starts to get a makeover. Here, fencing has been mounted on the approach to the left and the wall columns erected ready for the park fencing.
P3100141a.JPG (97944 bytes)

Detail of the park fencing in position, with work still on-going on the Park itself.   (>>)

P5150064a.JPG (124518 bytes)
And here is the finished park complete with grass, flower beds, benches, people etc.  (>>)
P5150065a.JPG (97599 bytes)
I wanted a stone statue of a soldier on a horse in the park. When I eventually found one, it had to be modified as it was far too big for my small park - but it is still imposing on its plinth!  (>>)
P5150057a.JPG (128299 bytes)
A view from the front. The roundabout still needs to be finished. (>>)
P5150058a.JPG (143092 bytes)
Otherwise, this area is now quite pleasing. (>>)
P5150067a.JPG (104106 bytes)
Anyway, the whole thing seems to have worked out really well for the space I had to do this.  (>>)

DCC (Digital Command Control).

A Bachmann E-Z Command unit can be seen on the right. I plan to have companion units for further trolleybuses, so I don't have to select the right code to change vehicles - simply use the correct controller.
The next one will fit in the space at the side, displacing the DC hand-held controller seen here. The knob above it is to switch the overhead between DCC and DC for evaluation purposes. I'll probably leave this in place to provide a backup in case of failure of either system.
PC200079a.JPG (87214 bytes)
Control panel with DCC and DC controllers in place. A Trix DCC hand controller has now been obtained, and this will program the CV's which the Bachmann unit won't. Note that some of the bus stop switches are 'on' in this view (they are lit up). (>>)
P1050098a.JPG (47533 bytes)
The DCC chip fastened to the ceiling of the lower deck in the trolleybus, where it is out of sight. The Gaugemaster chip  has a plug on it, so I can now easily separate the chassis from the body without having to unsolder wires.  (>>)

A 1960's style office block has been obtained - from Australia ! I had been searching for something appropriate for ages, and this turned up on ebay. This is how it arrived. It had to be completely 'knocked down' into its main parts so that I could reconfigure it to the right shape for the location on the layout. It needed to be more triangular and the exterior cladding would be altered. (>>)

Here the shell has been reconfigured into its new shape, and levelled up to suit the location between the Town Hall and the park. The upper floors have been reduced to 6 instead of the 8 original ones to make it closer to '00' rather than 'H0'. This side of the building features a colonnade inside the pillars. Structural steelwork has been reinstated. The shop windows have also been installed but these still require interiors.  (>>)

A first view from the other side, showing that one floor is still 'To Let', indicating the recent completion of this town centre building.
Still to be added are the cladding sheets much loved of tower block designers of the 1960's.
The interior is simply matt black to provide the lack of a view inside as many of these office blocks had.

As can be seen, this office block will be quite imposing and reminiscent of 60's-style developments.   (>>)

 

The Office Block now with its blue cladding sheets in place (the dots of white on the windows are advertising or office memos stuck on). The shop windows, however, still have to be detailed. This shot was taken at the Sandtoft Model Weekend in September 2008 and show how this end of the original layout is virtually complete.
(>>)

The shop window units ready for installation. There are windows for decorative plates (even special edition Beatles plates!), everyday crockery, sweets and model railways.

The picture on the right is a front view after the shop windows have been installed, various detailing jobs done on the interior and people added.   (>>)


The 'colonnade' side of the shops - Kaye's department store who are holding a Sale - showing the crockery section. The town centre looks somewhat busier now with the addition of lots of people. (>>)

The entrance to 'Electric House' - ie. the office block, at the back. (>>)

The third side showing schoolboys examining the model railway window, and the chocolate shop. (>>)


Shot after detailing has been added to the back yards of the parallel rows of houses, including the first of some gas lamps on the layout. (>>)


While in 'detailing mood' I decided to re-visit the shops and houses board. Here a long-planned wall, railings and people finish off the front. The awning still works on Peabody's shop and amazes people who see it being extended or retracted.  (>>)

And behind the shops in the block of four houses, there is a mother and daughter hanging out the washing while next door has the window cleaner in.  (>>)

After the 2013 Huddersfield exhibition I vowed to get on with motorising more road points (only Boards 5 & 6 had been done). This was because I had two operators controlling the trains while I did the buses and trolleybuses. They got in the way of me manually operating the road points on Board 3, which is the most complex, being the town centre.

I have had the point motors and DCC decoder kits in stock for a long time, so I've got on with it now. To the right are pictures of this difficult process (which is why I haven't done it before), squeezing these into the narrow space under the roads but above the railway.


The 'middle' four point motors added and connected to the respective manual rods, which I am leaving in place. The electrical connecting wires running off the back will go to the decoders when I've built them from the MERG kits as for Boards 5&6 (see extension pages). The lamp is only there to enable me to see!  (>>)

A further view showing the left-hand three point motors fitted beyond the four shown previously. That makes 11 altogether - the other three are spread out to the right of this view. That finishes the point motor installation, so its down to soldering up the decoders and getting them programmed, fitted and wired up.  (>>)

The Encoder (left) in the control panel. By adjusting the plug-in connector, the Decoder (right) can be programmed, or tested from the Encoder. Here is Decoder no.5 being programmed. (>>)

A view under the roadway baseboard showing Decoders 5 and 7 in place and wired up to the point motors. I have just used the odd numbers so I can insert even numbered ones inbetween in future if required. It also makes the panel switch wiring easier. (>>)

Here is the modified control panel complete with the 11 new switches in the Town Centre to operate the points. These are the small ones, the larger ones are for the bus stop solenoids.  (>>)

2016/2017 has seen some changes to the layoutbelow. One obvious one is that the roundabout has been finished at last, complete with 3D printed Huddersfield-style 'KEEP LEFT' bollards  (>>)

Colour-light signals are appearing on the railway as of 2017. Here D1500 is awaiting release from the station starter signal.    (>>)

D1500 gets the green light to enter the tunnel. The signal for the opposite direction can also be seen.
(>>)

 The opposite signal heading in the direction of the station features a 'feather' for the back platform road. (>>)

On the right is D6984 waiting at the newly installed starter signal on the back platform road. (>>)

And on the far right, the same loco is stopped at the new starter signal for the opposite direction. The starter for the Branch off the main line is also at red. Just to the left of the signal box there is a junction signal for trains coming out of the tunnel. In front of the signal box is the starter signal for the main line (on green), and to the right of that, just visible, is the incoming signal for the opposite main line. (>>)


 

 

 

Main Ridings page Layout - Early Layout - Development Extension

Layout - Overhead

Vehicles